Petrowsky v. Nextera Energy Resources, LLC

United States District Court, D. Kansas

June 21, 2017

EDWIN R. PETROWSKY, and LISA L. PETROWSKY, Plaintiffs,
v.
NEXTERA ENERGY RESOURCES, LLC, et al., Defendant.

          MEMORANDUM AND ORDER

          ERIC F. MELGREN UNITED STATES DISTRICT JUDGE.

         Plaintiff Edwin Petrowsky opposes the erection of wind towers anywhere in the Aransas-Wood Buffalo migratory population flyway. He does so because whooping cranes migrate through that flyway during several months each year. With that in mind, Petrowsky brings this citizen suit under the Endangered Species Act (“ESA”). He asserts that Defendant NextEra Energy Resources, LLC, and several of its subsidiaries are responsible for the erection of dangerous wind towers and accordingly, he seeks injunctive relief. Before the Court is NextEra's motion to dismiss (Doc. 19). NextEra contends that the Court lacks subject matter jurisdiction because Petrowsky failed to comply with the ESA's requirement that he notify each of its subsidiaries prior to bringing suit. Additionally, NextEra argues that it is not a proper Defendant in this case because it does not directly own or operate the wind farms in question. For the reasons stated below, the Court grants NextEra's Motion to Dismiss.

         I. Factual and Procedural Background

         This case relates to wind energy farms located in Pratt and Kingman Counties in Kansas. Edwin Petrowsky contends that those wind farms pose an imminent threat to the whooping crane-an endangered species. He asserts that the wind farms are located in the Aransas-Buffalo Wood migratory flyway, through which whooping cranes migrate annually. According to Petrowksy, whooping cranes will be killed or injured if they contact the blades of the wind turbines that make up these wind farms. Petrowsky believes that NextEra is responsible for these perceived violations of the ESA, and he seeks injunctive relief. Petrowsky ultimately requests a permanent injunction against the construction of wind farms in the Aransas-Buffalo Wood flyway, and an order to dismantle those that have already been erected.

         This is actually the second case that Petrowsky has filed against NextEra. In November 2016, Petrowsky filed his first ESA suit against NextEra. As with the instant case, he sought injunctive relief related to the alleged construction of wind towers by NextEra. NextEra filed a motion to dismiss, arguing that Petrowsky had failed to comply with the ESA's notice requirement. Under the ESA, a citizen suit may not be commenced “prior to sixty days after written notice of the violations has been given to the Secretary [of the Interior], and to any alleged violator of any such provision or regulation.”[1] Petrowsky admitted that he had not provided such notice, and the case was dismissed. During the briefing in the first case, NextEra represented in a footnote that Petrowsky had not identified the proper defendant without elaborating further.

         Petrowsky proceeded to send notice to both NextEra and the Secretary of the Interior. In that letter, dated December 6, 2016, Petrowsky asserted that NextEra was violating the ESA by constructing and operating wind farms in areas that will take whooping cranes without having obtained an incidental take permit. The letter was sent via certified mail to both the Secretary of the Interior and NextEra's registered agent. More than 60 days later, on February 21, 2017, Petrowsky filed the instant action.

         NextEra moved to dismiss Petrowsky's Complaint, asserting in relevant part that NextEra was not a proper defendant. Rather, NextEra represented that its subsidiaries-Ninnescah Wind Energy LLC, Kingman Wind Energy I LLC, and Kingman Wind Energy II LLC-were the proper defendants. NextEra noted that it “does not directly own or operate any wind turbines in Kansas.” Instead, NextEra asserts that the above-named subsidiaries developed, constructed, own, and operate the wind farms in question, and are the proper defendants in this case.[2] In response to NextEra's first motion to dismiss in this case, Petrowsky filed an Amended Complaint. The Amended Complaint added Lisa Petrowsky as a plaintiff. It also added as defendants the subsidiaries that NextEra had identified in its motion to dismiss (the “NextEra Subsidiaries”).[3]

         Notably, the Amended Complaint did not remove NextEra-the original defendant- from the case. Petrowsky still alleges that NextEra, together with the NextEra Subsidiaries, is violating the ESA. Specifically, he asserts that NextEra representatives initiated the project by drafting an environmental impact statement and gaining approval for the wind farm projects from the Pratt County Commissioners. He also alleges that NextEra has exercised a degree of control over the projects. Furthermore, he contends that the NextEra Subsidiaries are merely NextEra's alter egos, and as such, NextEra should be held liable for their conduct.

         However, many of Petrowsky's allegations are confined to certain subsidiaries. For example, he alleges that after the Pratt County Commission approved the wind project, “Ninnescah Wind Energy, LLC began construction. Ninnescah Wind Energy, LLC has finished construction of the farm and it began producing power in December.” He asserts that whooping cranes are present “where Ninnescah Wind Energy, LLC eventually built wind turbines and where Pratt Wind, LLC plans to build wind turbines.” Petrowsky also alleges that he had informed county commissioners that “the Ninnescah Wind Energy, LLC farm was now violating the Endangered Species Act and that the Pratt Wind, LLC farm would violate it” in the future. Elsewhere in his Amended Complaint, he again asserts that “whooping cranes regularly use the area where the Ninnescah Wind Energy, LLC; Kingman Wind Energy I, LLC, and Kingman Wind Energy II, LLC wind farms sit.”

         In his Amended Complaint, Petrowsky alleges that when he sent notice to NextEra and the Secretary of the Interior, he did not know about the NextEra Subsidiaries. Nevertheless, the Amended Complaint alleges that the notice “was specific enough” to put NextEra on notice that its subsidiaries were violating the ESA. He asserts that neither NextEra nor its subsidiaries have received an incidental take permit from the Secretary of the Interior. The relief he seeks is a temporary restraining order, and ultimately, a permanent injunction against the erection of any wind towers within the Aransas-Wood Buffalo flyway. Further, he asks that the Court order the dismantling of any towers that are currently violating the ESA. Although his sought remedies address any wind farm in the Aransas-Wood Buffalo flyway and any wind towers that are violating the ESA, his factual allegations all revolve around wind farms located in Pratt or Kingman County.

         The Amended Complaint mooted NextEra's first motion to dismiss, but NextEra has since filed a motion to dismiss the Amended Complaint, which is now before the Court. NextEra notes that Petrowsky did not send his 60-day notice to any of the NextEra Subsidiaries. For that reason, NextEra contends that the Court lacks subject matter jurisdiction over Petrowsky's claims against its subsidiaries. And because the Court lacks such jurisdiction, NextEra further argues that the case against NextEra should also be dismissed because there would be no underlying claim in which Petrowsky could attempt to pierce the corporate veil. Alternatively, NextEra renews its argument that it is not a proper Defendant in this case. Petrowsky disagrees, arguing that the letter he sent to NextEra satisfied the ESA's notice requirement with respect to the NextEra Subsidiaries. Thus, he contends that the Court has subject matter jurisdiction, and his case should be allowed to proceed.

         II. Discussion

         A. Subject Matter Jurisdiction

         NextEra argues that the Court lacks subject matter jurisdiction over Petrowsky's claims against the NextEra Subsidiaries. NextEra contends that those subsidiaries are not its alter egos; rather, NextEra and its subsidiaries are distinct entities. But NextEra fails to explain how it has standing to argue a 12(b)(1) motion on behalf of its separate and distinct subsidiaries. Nevertheless, “[f]ederal courts ‘have an independent obligation to determine whether subject-matter jurisdiction exists, even in the absence of a challenge from any party.' ”[4] If the Court determines that it lacks subject matter jurisdiction, it must sua sponte dismiss the action.[5]

         The ESA's 60-day notice requirement is jurisdictional and the Court lacks subject matter jurisdiction where a plaintiff has failed to comply.[6] Therefore, to adequately plead subject matter jurisdiction, Petrowsky's Amended Complaint must show compliance with the 60-day notice requirement. The notice requirement is to be construed strictly.[7] Indeed, the Tenth Circuit has dismissed a plaintiff for failing to satisfy the Clean Water Act's similar notice requirement where another plaintiff had already put the defendant on notice of the claims against it.[8] Constructive notice will not satisfy the ESA's notice requirement: strict compliance is required.[9]

         With that in mind, the Court first dismisses Lisa Petrowsky as a plaintiff. Her name is not included in the notice that was sent to NextEra, and there is no allegation that she separately sent such notice. Each individual plaintiff must provide notice to satisfy the ESA's notice requirement.[10] Because Lisa did not send such notice, the Court lacks subject matter jurisdiction over any ESA claim she may have.

         As for Petrowsky, he asserts that his notice to NextEra satisfies the ESA's notice requirement as to the NextEra Subsidiaries because the notice “was specific enough . . . to put both NextEra and the Department of the Interior on notice” that the subsidiaries were violating the ESA. But as noted above, constructive notice will not satisfy the ESA's notice requirement. Accordingly, the Court rejects that argument. However, Petrowsky also alleges that the NextEra Subsidiaries are merely NextEra's alter egos. “Generally, the separate corporate status of a parent corporation and its subsidiary will be recognized.”[11] But in certain circumstances, “[o]ne corporation may be the alter ego of another corporation; thus, the two corporations will be treated as one.”[12] Therefore, if Petrowsky has adequately alleged alter ego liability, then he has also adequately alleged subject matter jurisdiction, because in such a circumstance, providing notice to NextEra also provides notice to the NextEra Subsidiaries.

         Allegations of alter ego liability are governed by the liberal notice standard of Rule 8(a).[13] The Court looks at two factors in determining whether to pierce the corporate veil under an alter ego doctrine: (1) whether there is such unity of interest and lack of respect given to the separate identities of the corporations as to render the entities indistinct; and (2) whether adherence to the corporate fiction would sanction fraud, promote injustice, or lead to an evasion of legal obligations.[14] A plaintiff can plead alter ego liability by alleging the parent company exercised dominion and control over the subsidiary or disregarded legal formalities.[15]Furthermore, the alter ego doctrine is one of equity.[16] Therefore, its application is only appropriate if it appears from the plaintiff's allegations that some inequity could result from the misuse of the corporate form.[17] “Courts generally apply the alter ego rule with great caution and reluctance.”[18]

         Even accepting his allegations as true, and construing his pro se pleadings liberally, the Court cannot conclude that Petrowsky's allegations warrant application of the alter ego doctrine. In his Amended Complaint, Petrowsky alleges that NextEra has “exercised control over the project, spoken with citizens in Kansas, and acted in other ways as to be liable on alter ego and other theories that allow piercing the corporate veil.” Whether or not NextEra representatives spoke with citizens in Kansas is irrelevant to the issue of alter ego liability. And the assertion that NextEra has “acted in other ways” as to be liable as an alter ego is a conclusory allegation to which the Court affords no weight.[19] That leaves the Court with Petrowsky's assertion that NextEra has “exercised control” over the project, but he fails to explain the extent of that control. Nor does Petrowsky allege a lack of respect displayed for the separate identities of NextEra and its subsidiaries. Rather, his allegations seem to recognize the distinction between NextEra and its subsidiaries. At one point, the Amended Complaint states that “the Pratt County Commission approved the wind project and Ninnescah Wind Energy, LLC began construction. Ninnescah Wind Energy, LLC has finished construction of the farm and it began producing power in December (emphasis added).” In that allegation, Petrowsky asserts that Ninnescah, not NextEra, constructed and operates the wind farm in question. In several other instances, he alleges that a subsidiary, and not NextEra, is the party presently violating the ESA.

         Petrowsky also refers to a PowerPoint presentation that was allegedly cited during a Pratt County Commissioners' meeting. And although NextEra opposes reference to the document, it also fails to support Petrowsky's claim of alter ego liability. The presentation stated that “Ninnescah Wind Energy, LLC, a subsidiary of NextEra Energy Resources, LLC” is requesting approval for a wind energy project. In seeking approval, NextEra represented that it owns and operates over 100 wind projects in North America. But the presentation did not suggest that NextEra would actually be constructing or operating the Ninnescah wind farm. Rather, although the presentation conveyed that NextEra is Ninnescah's parent, and was active in gaining approval ...


Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.